St. Joseph Hospital Facade Removal
Savannah, GA
Complete removal of the exterior facade, brick and precast, of a 7 story hospital through the mixed use of hammering, sawing, rigging, and scaffold lifts. The project was completed ahead of its aggressive schedule. Also included were highly-phased renovations to the patient rooms located throughout the hospital.
Owner/Client:
Rives E. Worrell
Project Summary:
• Exterior facade removal from 7-story hospital.
• Utilized hammering, sawing, rigging and scaffold lifts to complete the exterior work.
• Facade removal completed ahead of schedule.
• Selective interior demolition on phased schedule completed in May 2015.
Project Completed:
Facade Removal Portion of Contract: July 2013 - Feb 2014
Interior Selective Demo:
April 2014 - May 2015